Kids Zone seeks $1 million by May to break ground on expanded children’s museum
Summary
Kids Zone told the Truckee Town Council it has raised about $6 million toward a two‑phase project with a $9 million Phase 1 and urged municipal and community support to reach a May fundraising milestone to qualify for a rural nonprofit loan.
Get email alerts on the Early Education topic
No spam. Unsubscribe anytime.
Kids Zone’s leadership told the Truckee Town Council on April 1 that the children’s museum has raised roughly $6 million — about 67% of the Phase 1 goal — and that it needs roughly $1 million more by May to qualify for a low‑interest rural nonprofit loan and begin construction this summer.
Why this matters: The project aims to expand capacity, add STEAM and sensory spaces, and serve more underserved families; staff and the museum said the expanded facility would increase local economic activity and year‑round visitation.
Carol Maher, director of Kids Zone, presented a two‑phase plan for a new Regional Park museum building. Phase 1 is budgeted at $9,000,000 and includes a STEAM center, a sensory “sunrise spot,” toddler and climbing areas, restrooms and flexible program space; Phase 2 is estimated at $3,000,000 and would add a children’s art room and gallery space. Maher said the museum has raised $6,000,000 — “67 percent of our goal” — and is targeting $1,000,000 by May to improve its loan eligibility and break ground this summer. She said a prefabricated (metal) building will reduce construction time to an estimated 18 months.
The presentation described program features intended to serve preschoolers, underserved families, seniors and teens, and to host traveling exhibits and an expanded outdoor play and education area. Maher highlighted plans for an on‑site teaching kitchen, a teen creative studio and cross‑generational programming near a senior housing area.
Council and public questions focused on timeline and fundraising strategy. Maher said Kids Zone has conducted a quiet “silent phase” campaign targeting major donors and is preparing to broaden outreach to the public. She said the organization is also working with Parks and Recreation staff and lenders that provide rural nonprofit loans.
Clarifying details provided at the meeting: Phase 1 estimated cost $9,000,000; Phase 2 estimated cost $3,000,000; funds raised to date approximately $6,000,000; target to raise an additional $1,000,000 by May to help qualify for a loan; estimated build time once started: 18 months. Maher gave a contact phone number for donor inquiries and said the museum had applied for a building permit.
Ending: Council members and speakers encouraged community support and said the town would continue to coordinate with Kids Zone staff on permitting and partnerships. No town funding commitment was made at the April 1 meeting.