Design moves forward for Adler Road bond project; culvert designs complete, construction slated for 2026
Summary
City engineers reported progress on Adler Road design work tied to the 2022 bond; culvert designs are complete, three of four required properties for culvert work have been acquired, and roadway construction is planned to start in 2026.
Get email alerts on the Transportation Adler Road topic
No spam. Unsubscribe anytime.
Boerne city staff gave a progress update on the Adler Road bond project on March 25, reporting that culvert designs are complete, property acquisition for the culverts is nearly finished and broader roadway design work is underway.
Director Jeff Carroll said the design phase began after the 2022 bond measure and that surveying required right‑of‑entry letters from 24 landowners. He told the council the culvert designs are 100% complete and three of the four properties needed for that work have been acquired; staff is working on the remaining parcel.
Carroll described the overall roadway project as converting most of the corridor from a two‑lane pavement into a three‑lane section with a continuous two‑way left‑turn lane, adding a five‑foot sidewalk on the south side and a 10‑foot sidewalk on the north side, installing curbs and making significant storm‑drain improvements. The city expects to receive a 60% design submittal from the consultant in the summer and is planning to begin construction in 2026.
Why it matters: staff said the center two‑way left‑turn lane and storm‑drain improvements will reduce congestion and address drainage issues in the corridor. The work follows the bond‑referendum schematic and moves design toward construction after preliminary property work and culvert designs.
Ending: council members were invited to raise questions; no final construction contract or funding amendment was presented at the March 25 meeting.