Transit trust accepts 30% transfer‑center design, directs staff to continue full design and bid documents

2769413 · March 26, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Transit Trust accepted a 30% design for a transfer center (phase 1) repurposing an existing police storage building, received a cost estimate near $3.6 million for phase 1, and directed staff to contract for the remaining design and construction documents so the project can move toward bid and permitting.

The Lawton Transit Trust accepted a 30% design for phase 1 of a proposed transfer center and directed staff to pursue contracts for the remaining design and construction bid documents.

Design presentation and scope

Architects from Wendell W.D. Architecture presented a phased plan that reuses part of a police storage building for a conditioned 2,500‑square‑foot transfer center and a covered 12‑bay bus platform. Phase 1 would create passenger waiting space, staff offices and covered bus canopies; later phases could add maintenance and service capacity if funding allows.

Cost and schedule

The consultant team provided a preliminary construction cost estimate for phase 1 at about $3.6 million, including contingencies and escalation. The trust heard the 30% design is conceptual and that additional design milestones (60% and 90%) are required for bid documents and permitting; staff said the 30% package was produced to support grant applications and initial funding requests.

Trust direction and vote

Trust members voted to accept the 30% design and to direct staff to negotiate a contract for remaining design and construction documentation. The motion carried unanimously at the trust meeting.

Context

Trust and staff said the transfer center design assumes relocation of an evidence/storage function currently in the building; that relocation and its costs are not included in the transfer‑center estimate and would be handled separately. The trust noted federal grant applications will require shovel‑ready documentation and said completing the design is a prerequisite for future construction and grant funding.

Ending

Staff will return with the negotiated contract for remaining design work and with updated cost estimates as the project advances through 60% and 90% design milestones.