Board authorizes $10.12 million change order for Cobbs Creek Reservoir construction and up to $190,000 for pump seals

2769232 · March 25, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Henrico supervisors approved contract change orders totaling $10,123,837.05 to address outstanding claims and design changes for the Cobbs Creek Reservoir project and authorized a final change order not to exceed $190,000 for raw-water pump seals; funding will come from the Water and Sewer Revenue Fund.

The Henrico Board of Supervisors on March 25 approved two construction change orders for the Cobbs Creek Reservoir project that together total more than $10.3 million.

Mister Chan (Public Utilities Director) told the board the project reached substantial completion on Nov. 8, 2024, and county staff and the contractor had negotiated a change order for $10,123,837.05 to resolve outstanding claims for additional work and design changes. The Department of Public Utilities also anticipates a separate final change order to complete work on raw-water pump seals estimated not to exceed $190,000; Chan said funding is available in the Water and Sewer Revenue Fund.

Motion and outcome: A motion to approve the change orders (agenda item 95-25) was made, seconded, and adopted by the board (voice vote; no recorded opposition). County staff said the change orders are intended to resolve outstanding construction claims and complete remaining pump-seal work. Funding will be provided from the Water and Sewer Revenue Fund as presented by staff.