Council approves change order for temporary pavement to meet sight-distance on Topher Parkway
Summary
The Toquerville City Council approved Change Order No. 19 to add temporary pavement sections at the north end of Topher Parkway to meet site-distance requirements; council members discussed an additional cost of about $129,000 and mobilization charges.
Get email alerts on the Infrastructure Transportation topic
No spam. Unsubscribe anytime.
The Toquerville City Council on March 25 approved Change Order No. 19 to install temporary pavement sections at the north end of Topher Parkway so the site meets required sight-distance standards. Council discussion cited an additional cost of roughly $129,000.
A council member described the change order as an addition to a previously approved temporary paving item, explaining the temporary north-end pavement will remain until permanent work is finished. “That is to make the temporary access of 17 is paid properly,” a speaker said while discussing the north-end access. Another council member said the change order represents an additional cost of about $129,000.
Members again discussed mobilization charges and why contractors may charge extra when equipment must return to a site after leaving for other jobs. One council member described the process: “they mobilize they mobilize they mobilize... because if you came in and you did all the paving all at once, it'd be 1 mobilization. Problem is is they've got other jobs, so they'll take that those machines out because they gotta go do those jobs and then they'll come back at a different time and do this 1. That's what they're charging you for is the bridal and bringing all those equipment and to do the work.”
A motion to accept Change Order No. 19 was moved and seconded; the council recorded multiple “Aye” votes and the motion carried. The transcript records the amount as “a hundred and 29,000 extra” and also includes a brief back-and-forth about whether to state a specific dollar amount during the motion. The council did not specify a funding source for the change order in the recorded discussion.