Adams County project manager presented pay application and a final acceptance letter for Chester Willis Field sports lighting. The board approved a pay application for a contractor’s work but deferred final release of retainage until county staff confirm that newly installed safety lights come on via photocell and drainage issues are addressed.
Project manager Joey Burr (recorded as Joey Burr/Joey Furr in the minutes) told the Adams County Board that the Chester Willis Field baseball project has reached substantial completion and presented pay application paperwork for the contractor, Southern Electric Corporation.
Burr asked the board to approve pay application number 5 for $67,786.64, citing the board’s prior acceptance of substantial completion on Oct. 3. He said that release of retainage — pay application number 6, $15,260 — would follow final acceptance once the contractor completed the punch list. "This is their final payment of the retainage that we the money that we have…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat