City staff gave commissioners a training on 2023's Senate Bill 174 and how it changes subdivision review: planning commission will serve as the administrative land use authority (ALUWA) for preliminary plats while staff will handle final plats, with new review timelines and limits on rehearing preliminary approvals.
Get email alerts on the Land Use Subdivision topic
No spam. Unsubscribe anytime.
Willard planning commissioners received a staff training on recent state changes to local subdivision review procedures, including requirements from Senate Bill 174 that establish an Administrative Land Use Authority, city staff said.
The training, presented by staff member Maddie, explained that the statutory changes apply to subdivisions of one- and two-family dwellings and townhomes and require cities to designate an Administrative Land Use Authority, or ALUWA. "It does not include a municipal legislative body or even a member of the municipal legislative body," Maddie told commissioners when reading the state's definition.
The changes mean the planning commission — acting as the ALUWA at the preliminary stage in Willard — will review preliminary plats, hold the required public hearing and take final action at that preliminary stage. Final-plat review, including review of subdivision improvement plans (the civil engineering drawings for sewer, water, grading and other infrastructure), is an administrative step handled by city staff. If the ALUWA approves a preliminary plat, that preliminary approval cannot be revoked at the final stage, Maddie warned.
Why this matters: the revised process shortens some opportunities for council or commission reconsideration and places responsibility on commissioners and staff to catch required infrastructure details early. Maddie highlighted new statutory timelines: staff has 30 days to place a complete preliminary application on the planning commission agenda; a final application review phase gives staff 40 business days to complete a first review; applicants have up to one year after preliminary approval to submit their final application; staff and applicants may go through up to four review cycles before an automatic denial. Commissioners were also told the timelines shorten further if Willard's population exceeds 5,000.
Commission discussion focused on the practical effects of the new steps. Matt (commissioner) asked whether the subdivision improvement plans the commission will see at preliminary are the same as the final engineering sets; a staff member and engineer Chris Breinholtz confirmed the plans will be the buildable civil plans and stressed the commission must be thorough because missing an item at preliminary can let an applicant proceed without further commission review.
Staff walked commissioners through several firm deadlines that could lead to automatic approval or denial if missed: 15 days to schedule a requested pre-application meeting; seven days for staff to declare a preliminary submission complete or incomplete; 14 days for an applicant to cure an incomplete application; and 20 days for an applicant to respond after staff requests modifications during the final-application review cycles. Maddie said the city already has tracking tools and will use Civic Review to manage comments and alert reviewers when statutory clocks begin to run.
Commissioners and staff agreed to additional training and to give commissioners access to Civic Review as viewers so they can see staff comments before public hearings. Maddie said she will circulate the presentation and spreadsheets that track timelines when new applications start their review cycles.
The presentation closed with staff noting that one incomplete subdivision application has been received; its 30-day clock will begin once the applicant submits a missing plan or map.
The changes described in the presentation come from the 2023 legislative session's Senate Bill 174 and related state definitions for an Administrative Land Use Authority. The commission said it will schedule follow-up training and use Civic Review to help coordinate staff and commission comments.
ACTIONS: none formal on this item. STAFF FOLLOW-UP: staff to send the training slides and timeline spreadsheets to commissioners and to set up Civic Review viewer access.