District updates on ESIP, stormwater repairs and summer construction; Honeywell work under way
Summary
District officials reported progress on the Energy Savings Improvement Program (ESIP) with Honeywell, stormwater and stadium projects, lead fixture testing, and a slate of summer bids for library conversions, secure vestibules and an auditorium; administrators also described plans to relocate some central office staff to 79 Glover Avenue.
Get email alerts on the Facilities Capital topic
No spam. Unsubscribe anytime.
District facilities and finance officials gave a status update on several capital projects and maintenance programs, including ESIP work, stormwater repairs, ongoing and upcoming construction bids, lead testing results and facility planning.
Officials said Honeywell has started ESIP building‑envelope work (weather‑stripping, attic insulation, door seals) across district buildings; lighting upgrades were described as the next major ESIP phase. The district reported a preconstruction meeting scheduled for a stormwater pipe repair at the rear of the stadium and said other summer projects include converting existing libraries to classrooms or specialized OT/PT and small‑group spaces, completing an accessible stadium project, and posting bids for interior alterations and the new middle‑school auditorium.
Facilities staff reported lead testing (the district’s triennial testing) found a small number of fixtures that exceeded the action threshold; those fixtures were taken out of service and, according to principals, were not heavily used. Administrators clarified the required lead threshold is very low and described the consultant’s testing procedure.
The facilities update included timeline notes: bond sale scheduled for early April (district seeking favorable rates), an October–February timetable projected for the turf field (separate from the referendum projects), and fall/next‑spring timing for additional building conversions and the high‑school auditorium. Officials said some environmental findings (mercury‑containing flooring in specific spaces) will be remediated without extended shutdowns, saving time and cost.
Administrators also said they will upgrade public communications and the district website to provide clearer project timelines and progress tracking, and that the administration plans to relocate three content‑area supervisors to 79 Glover Avenue ahead of a separate plan to repurpose the old administrative office.
No final board action was taken on new contracts during the facilities report, though the board later approved routine awards and an RFP for custodial services during the consent vote portion of the meeting.
Sources: Facilities report to the board; staff comments during business and capital updates.