Oxnard staff recommends $6.0 million Onyx Paving contract for Phase 1 neighborhood resurfacing
Summary
City of Oxnard staff recommended awarding a $6,006,007.50 construction agreement to Onyx Paving Company for the citywide neighborhood street resurfacing project Phase 1, with total project funds of $7,207,209.50 and budget adjustments tied to multiple local funds and a CalRecycle grant.
Get email alerts on the Street Resurfacing topic
No spam. Unsubscribe anytime.
Tamara Flynn, construction project manager for Public Works Engineering, told the Oxnard City Council that city staff recommends the council approve a construction agreement with Onyx Paving Company in the amount of $6,006,007.50 for the citywide neighborhood street resurfacing project Phase 1 and authorize a 10% contingency of $600,601, for a total not-to-exceed construction amount of $6,606,608.50.
City staff presented the project as Phase 1 of the City of Oxnard's five-phase citywide pavement management program, and said the total project cost including construction, contingency and engineering, inspection, survey and project management is $7,207,209.50. "The lowest bidder was Onyx Paving Company," Flynn said during the presentation.
The Phase 1 work is planned for selected streets in the Cabrillo, Sierra, El Rio West, Rose Park, Pleasant Valley and Southwinds neighborhoods; Flynn also displayed maps that included Sea Air during the presentation. Staff said the average pavement condition index for the streets targeted in those neighborhoods is between 30 and 40, requiring corrective work. The staff presentation named mill-and-overlay asphalt paving for heavily damaged segments and slurry seals for less deteriorated segments, and said approximately 23% of work is pavement preservation.
Staff summarized the formal bid results: Onyx Paving Company $6,006,007.50 (lowest bidder); Toro Enterprises $6,128,564.60; Granite Construction Company $8,208,218.495.05; and Cia Rasmussen $10,752,944.70. After reviewing bids for compliance with city business requirements, staff recommended awarding the contract to Onyx.
Flynn outlined funding and appropriation changes for the project. She said budget appropriations totaling $1,215,946 are proposed, consisting of $127,968 from the water operating fund, $87,978 from the wastewater operating fund and $1,000,000 from Tax Allocation Bond (TAB) proceeds fund balances; staff said TAB proceeds will be used only for work in the Southwinds project area because TAB funds are restricted to specific areas and may have expiration dates. Staff also recommended unappropriating $158,998 from the Road Maintenance and Rehabilitation Account to offset a pro rata CalRecycle grant award for the project; Flynn told the council the CalRecycle Rubberized Pavement Program grant award was approved earlier and will offset that amount.
Flynn said the Phase 1 selection was advanced because La Colonia Phase 3 — previously the next scheduled neighborhood project — is delayed by right-of-way disagreements with seven property owners. She said staff moved forward with the Phase 1 neighborhoods so other projects would not be delayed.
The presentation included a staff recommendation that the mayor execute the agreement with Onyx and that the council approve the appropriation changes described. The transcript of the staff presentation did not record a council motion or vote on the recommendation.
Staff provided maps of the neighborhoods and a breakdown of project methods; further details, including final contract execution and any council votes, were not captured in the provided transcript excerpt.