Huber Heights staff recommend multiple road, utility and park construction awards; projects to appear on Monday agenda

2679743 · March 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff recommended awards or presented bid results for a series of capital projects including a mast-arm signal at Brant Pike & Fishburg, water-main replacements, sewer lining, curb/sidewalk work, a Chambersburg water tower repaint and other road projects; most awards were recommended to be placed on the formal Monday agenda for approval.

Huber Heights — At its March 18 work session, staff presented bid results and recommended contract awards for multiple public‑works and utility projects planned for 2025 and 2026. Council did not adopt final awards at the work session; staff asked that the recommended awards appear on the next formal agenda.

Projects and staff recommendations included:

- Brant Pike & Fishburg Road mast-arm traffic signal: Capital Electric submitted the low responsive construction bid at $595,324.49; staff recommended award to Capital Electric with a not‑to‑exceed authorization of $650,000 and an expected completion near year‑end (accounting for mast-arm lead times). (agenda item 3j)

- Brant Pike (Kershaw/Carriage Trails) intersection improvements: Integrity Contractors was the low bidder at $1,266,391.51; staff recommended award with a not‑to‑exceed figure of $1,425,000. Work includes turn lanes, pavement, signage and a mast‑arm signal; staff said lane improvements will open before signal installation. (agenda item 3n)

- 2025 Sewer lining: Viziu (Vizu) Sewer of Ohio was the low bidder at $342,298.95 to line approximately 6,700 linear feet of sanitary sewer; staff recommended awarding the annual lining contract and said the method prolongs pipe life. (agenda item 3k)

- Water-main replacement program (multiple areas/phases): Staff presented a multi‑phase water-main replacement program that would replace roughly three miles of water main in several neighborhoods; bids produced phased low bidders (Performance Site Development and M & T Excavating in various sections). Staff proposed spreading construction across seasons to obtain better pricing and preserve paving schedules. (agenda item 3l)

- Sidewalk and curb program: Colburn's Concrete was the low bidder for the sidewalk portion ($116,693) and the curb replacement portion ($756,600); staff said work would begin in spring and be completed prior to fall paving. Staff discussed how residents can elect to hire contractors directly and that permit/inspection requirements apply to privately contracted work in the right-of-way. (agenda item 3m)

- Chambersburg water tower repaint: L & T Painting (MI) was the low bidder at $518,600; staff proposed awarding the contract and required completion by August 1. The tower holds 1.5 million gallons and the last paint cycle was about 14 years ago. (agenda item 3p)

- East Water Main extension (Bellefontaine Road): staff reported the project is complete but requested a contract modification to cover an approximately $8,000 final cost overrun tied to an additional valve placed near the county line; the project was funded with ARPA and city sanitary funds. (agenda item 3o)

Staff emphasized scheduling constraints tied to mast‑arm lead times and seasonal paving windows. Councilmembers posed operational questions — for example, about calendar days listed in bids and sequencing work to minimize disruption near schools — and staff responded with sequencing and completion-date plans. Most items were moved to the Monday agenda for formal award and second‑reading waiver when appropriate.