Committee reviews ratification request for Peachtree Industrial Boulevard water-main emergency; item deferred to audit

2679722 · March 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

DeKalb County’s watershed director asked the Public Works and Infrastructure Committee to ratify an emergency purchase to replace transmission mains along Peachtree Industrial Boulevard, saying the work affects roughly one-third of county water service; commissioners deferred the item to audit for two weeks.

Director Wells presented agenda item 2025-0268 on March 6, requesting ratification of an emergency purchase for replacement of large transmission mains along Peachtree Industrial Boulevard.

The agenda description states the project consists of approximately 10,500 linear feet of 12-inch ductile-iron pipe and 10,500 linear feet of 36-inch ductile-iron pipe and requested ratification of an emergency contract awarded to Ruby Collins Incorporated in an amount not to exceed $46,435,928. Wells said the request will go to audit but provided context: he said roughly $6,000,000 of the total requested amount has already been spent on emergency mobilizations and material purchases, and that ductile-iron pipe has experienced longer lead times since the pandemic.

Wells described the transmission main as one of three feeding the county and said the line supplies water to roughly one-third of DeKalb County, including critical facilities such as Emory Hospital and the Centers for Disease Control. Commissioners asked clarifying questions about timing and costs; Wells said he will return with a detailed breakdown of expenditures and that the item would move through audit before returning to the committee.

The committee voted to defer the ratification for two weeks to allow audit and staff to provide additional documentation. Commissioners asked that the item be prioritized in audit because of its operational importance.