Rio Grande Trail paving project hits unexpected costs; county requests supplemental funds
Summary
Open Space & Trails staff told commissioners that retaining-wall work, rail removal, topsoil purchases and thicker-than-expected asphalt increased costs on the Rio Grande Trail and Crystal River Trail projects by roughly $310,000, prompting a supplemental funding request.
Members of Pitkin County Open Space & Trails told commissioners on June 10 that the 2025 Rio Grande Trail and Crystal River Trail paving projects ran into unanticipated conditions that pushed the budget over by about $310,000.
Ted O’Brien, presenting for Open Space & Trails, said crews encountered railroad tracks while digging for retaining walls where the railroad bed had shifted; removing the tracks cost about $127 per linear foot and required altered construction methods.…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat