Hallandale Beach CRA approves $328,041 increase for Northeast First Avenue streetscape project
Summary
The Hallandale Beach Community Redevelopment Agency on May 21 approved a $328,041 increase to the guaranteed maximum price for the Northeast First Avenue streetscape improvements project and discussed staging, parking impacts and a stakeholder meeting June 5.
Get email alerts on the Streetscape Transportation topic
No spam. Unsubscribe anytime.
The Hallandale Beach Community Redevelopment Agency on May 21 approved a resolution increasing the guaranteed maximum price for the Northeast First Avenue streetscape improvements project by $328,041.
Executive Director Dr. Earl said the project will be staged in roughly 300-foot sections and is expected to last as long as 18 months. "It will be messy and we are going to be losing a lot of those parking spaces in the short term," Dr. Earl said, adding the agency will work with maintenance-of-traffic consultants, the city engineer and contractors to reduce disruption.
Dr. Earl described plans to keep parts of the corridor open by alternating construction and parking areas, briefly converting sections of the one-way roadway to two-way traffic during work and exploring a shuttle or trolley linking the new FEC parking lot to the corridor. "We're going to be staging the project in sections... Have the ability to have, some type of maybe trolley system or something that goes, that helps people to go from the parking lot," he said.
The board also set a stakeholder meeting for Thursday, June 5, 2025, from 6 p.m. to 7 p.m. to update business owners and other stakeholders; Dr. Earl said CRA staff have been meeting in person with business owners along the corridor.
The resolution's reading included additional line items described in the meeting record as an owner's contingency of $120,000 and a permit-allowance figure that was garbled on the record and not specified in the transcript. The board authorized the executive director to execute contract amendments necessary to implement the increase.
Votes at a glance
- Approval of minutes from the March 19, 2025 meeting — approved by roll call, 5-0. - Consent items A–D (excluding item C) — approved by roll call, 5-0. - Resolution approving the increase to the guaranteed maximum price for the Northeast First Avenue streetscape improvements project — approved by roll call, 5-0.
The board conducted roll call votes for each measure; the roll calls recorded five affirmative votes and no negatives or abstentions.