Supervisors approve $168,235 change order for North Star Industrial Park access loop
Summary
The board unanimously approved change order No. 2 for site work at North Star Industrial Park, adding fresh stone to a constructed loop road to improve access for prospective industries. The project uses ARC and Mississippi Development Authority grant funds matched with city and county bond proceeds.
Get email alerts on the Economic Development topic
No spam. Unsubscribe anytime.
The Oktibbeha County Board of Supervisors unanimously approved change order No. 2 totaling $168,235.25 on March 17 for additional stone work at North Star Industrial Park to improve the drive and access around a future building pad.
Why it matters: The project is part of a multi-million-dollar site-development effort that includes Appalachian Regional Commission (ARC) funds, an ARC application of $2,719,102 and a Mississippi Development Authority (MDA) site-development match. The county and city have committed bond proceeds as local match. The road and pad work is intended to make the site show-ready for prospective industries.
County planning and economic development staff described the funding package: an ARC application and an MDA site-development grant left several million dollars in combined funds, part of which has been used for grading and a building pad. Burns’ Dirt (contractor) was previously obligated for initial grading under the original contract and change order No. 1; the current change order will place fresh stone on the loop road and stabilize a drive used by industrial prospects.
Staff said the loop road is intended as permanent site access and will tie into future roads as the park develops. Supervisors asked whether pond fill work and other site tasks were included; staff clarified those items and said some features were outside the current contract scope. The board approved the change order on a unanimous vote and directed staff to finalize contract documents.