Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Utilities Infrastructure topic

No spam. Unsubscribe anytime.

Commission approves $18,037.40 payment to relocate waterline at Crooked Bridge

2628071 · March 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved payment of $18,037.40 to relocate a county waterline that conflicts with a Georgia Department of Transportation bridge replacement on Highway 220 (Crooked Bridge); commissioners approved using American Rescue Plan funds to cover the cost.

The Lincoln County Board of Commissioners approved payment of $18,037.40 to relocate a county waterline that conflicts with a Georgia Department of Transportation bridge replacement project on Highway 220, known locally as Crooked Bridge.

Public Works staff reported an initial county engineering cost estimate of about $180,000 for the relocation. County discussions with GDOT and other parties reduced the county—ost share through successive negotiations to $18,037.40. Staff asked the board to approve the payment and recommended funding it from the county merican Rescue Plan (ARP) fund; the board approved that recommendation on motion and voice vote.

County officials explained the relocation is required when the state designs a bridge replacement that conflicts with on-site utilities; if a utility must be moved to allow the highway work, the utility owner typically bears some or all of the relocation costs unless state aid or other arrangements apply. The approved payment will allow the bridge project to proceed without delay.

Ending

Public Works and Finance will complete the payment from ARP funds and document the expense in project records.