Summary
The county signed a construction contract for the 18 Mile Road bridge over Plumburg Drain, approved bridge-management contracts and revised a cost-share agreement with the city; departments also recommended support for an Anchor Bay Schools Safe Routes to School grant application.
Get email alerts on the Infrastructure Bridges topic
No spam. Unsubscribe anytime.
Macomb County commissioners approved a construction contract and related agreements for bridge work on 18 Mile Road and authorized contracts for the county’s biennial bridge inventory, while also voting to support a Safe Routes to School application by Anchor Bay Schools.
County roads staff asked the committee to approve a contract with Z Contractors Inc. for rehabilitation of the 18 Mile Road bridge over Plumburg Drain and noted the project is a 50/50 local agency project with the city. The county’s share was described in committee as roughly half of $1,375,000 in total project cost.
County staff also presented a revised cost-share agreement amending an earlier estimate dated Jan. 24, 2025 because changes in the project total changed the allocation of design and construction costs; the updated city contribution was described in the material as $403,939 (revising a prior $1,171,000 number shown earlier in the file).
Separately, the department requested contracts to provide bridge inventory and management services through a biannual external inspection of about 240 county bridges. Staff said Great Lakes Engineering Group and Spicer Group were selected from an RFQ and estimated anticipated costs for bridge-management services of approximately $175,000.
Finally, staff introduced a resolution supporting Anchor Bay Schools’ application for Safe Routes to School funding. The county’s materials state the district is seeking $2,000,000 in grant funds and requested the county show departmental and county support for the application.
Commissioners asked technical questions about the scope of bridge inspections — whether they include core sampling or are visual and metric-based, and whether the bridge work would require full closures. County roads staff said the external inspections evaluate 35–40 metrics across bridge elements (deck, beams, abutments) on a biannual basis and that the 18 Mile Road work is rehabilitation, not full replacement, and will mostly be done under traffic control; only limited closures (for example for epoxy coatings) might be necessary.
The committee voted to recommend the items to the full board; the clerks recorded the motion carrying unanimously in committee.
Members of the public were not recorded speaking on these items during committee discussion.