Council reviews several water and wastewater infrastructure items: Well 5 rehab, spare motor, odor curtain and testing contracts
Summary
Staff briefed council on a series of water/wastewater projects and procurement items: a not‑to‑exceed request to complete Water Well 5 rehab, a bid recommendation for a 400‑horsepower motor, an odor‑control curtain for the wastewater plant, and material testing for Water Plant 32.
Get email alerts on the Water Wastewater topic
No spam. Unsubscribe anytime.
At the March 12 workshop city staff reviewed several water and wastewater infrastructure items and procurement recommendations.
Water Well 5 rehab: Staff reported a catastrophic down‑hole equipment failure at Water Well 5 and said initial exploration revealed a blockage in the upper screens that required specialized jetting and rigs. Staff described the $105,992 line item as the year‑one expenditure shown in the packet but recommended a not‑to‑exceed value up to $140,000 to cover unforeseen conditions while crews investigate the down‑hole condition and proceed with cleanup and rehabilitation. Staff said a more precise condition assessment will follow once crews complete the work.
400‑horsepower motor (spare): The council was briefed on a competitive solicitation for a spare motor for Water Well 27. Staff recommended awarding to Lufkin Armature as the low bidder for a motor price of $64,776. Staff described the purchase as a critical capital spare; no formal award occurred at the workshop.
Odor control curtain enclosure at Conroe Central Wastewater Treatment Plant: Staff proposed installing odor curtains on three sides of the headworks to reduce odors carried by easterly winds. The recommended contract was $79,967, to be funded from prior bond proceeds; staff characterized the curtain as the remaining piece of odor controls at the plant and said earlier mechanical options were obsolete or unavailable and more costly.
Material testing for Water Plant 32: Staff recommended contracting Geoscience to provide construction material testing and quality control services for Water Plant 32. The proposed amount was $75,000; staff noted Geoscience had already performed geotechnical work for the foundation and the purchasing group recommended continuity of consultant services.
Why it matters: staff said the Well 5 failure is an immediate operational matter that requires repair to restore reliable water production. The spare motor purchase and testing contract are preventive asset‑management items; the odor curtain is neighborhood‑focused mitigation.
Next steps: staff said they will return with updated condition assessments, finalized contract documents and any proposed not‑to‑exceed language for council action. No formal contract awards or appropriations were recorded at the March 12 workshop.