SFPUC reports $404 million spent so far on 22 Hetch Hetchy capital projects; major shutdowns completed

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The PUC reported progress and cost forecasts for 22 Hetch Hetchy projects, noted recent 100‑day system shutdown completion, and outlined cost increases on Moccasin and reservoir projects.

Katie Miller, director of water capital programs, summarized the Hetch Hetchy Capital Improvement Program through Dec. 31, 2024. The program now tracks 22 projects across water, power and joint categories with a combined budget of $1.9 billion; $404 million has been spent to date and $65 million was spent during the first two quarters of the fiscal year.

Miller told commissioners that 14 projects are in preconstruction, seven are in construction or multi‑phase including construction, and one is in closeout. She described several specific items: a forecasted $15 million cost increase…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans