Hermosa Beach outlines Pier Avenue paving, pier testing and library accessibility work ahead of spring season
Summary
City staff detailed timing and steps for Pier Avenue and Parking Lot A resurfacing, overnight pier sensor testing and LA County-funded accessibility upgrades at the Hermosa Beach Library; crews aim to finish major downtown work ahead of Memorial Day.
City staff told the Hermosa Beach City Council on March 11 that Pier Avenue resurfacing and repairs to Parking Lot A are scheduled to begin in April with the goal of completing major paving work before the Memorial Day holiday.
Public works director Joe San Clemente said the contractor will not close Pier Avenue to traffic and will phase work to preserve two-way traffic and minimize impacts to downtown businesses. He said most pre‑paving activities — land surveying, concrete ramps and minor sidewalk repairs — could span about five weeks but will not significantly affect traffic or parking. Grinding and repaving operations on Pier Avenue are expected to take two to three days for the roadway and about a day for Parking Lot A; work will be phased to reduce parking disruption. "We expect paving work will take about a day for Parking Lot A and 2 to 3 days on Pier Avenue," San Clemente said.
San Clemente also described…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat