Engineering updates 2025 street projects; downtown work ahead of schedule, phased neighborhood projects under way
Summary
Engineering reported progress on multiple 2025 reconstruction projects: downtown Washington/Third/Jackson is ahead of schedule; Randolph/Cherry phases are advancing; Fulton, First and River Drive work is progressing; a multiuse trail near Sunnyvale Park is on track for an early August completion.
City engineering staff provided progress reports on the 2025 street reconstruction program and related projects at the committee's June 12 meeting.
Downtown: The Washington/Third/Jackson downtown work is described as proceeding "extremely well" and is ahead of schedule. Washington Street from First to Third is open to traffic; paving is complete from Third to Fourth but final landscaping and finishing will keep full reopening later; concrete pours on Third Street (south of Washington toward Jackson) are underway.
Randolph and Cherry (Project A): The work is split into three phases. Phase 1 (Cherry Street from West Wausau…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat