District staff report summer progress on Palmer and Jenkins renovations and wide capital work across schools
Summary
District facilities staff reported on summer capital work, including abatement and enabling work at Palmer, preparatory work at Jenkins, numerous playground and security-entrance projects at elementary and middle schools, and a five‑year capital plan that outlines needs for all district schools.
District 11’s capital programs team updated the board on summer projects and a newly completed five-year capital plan at the June 11 meeting.
Palmer and Jenkins - Palmer High School: Contractors are completing asbestos abatement and enabling work; staff said utilities and temporary accommodations are in place while phased renovation proceeds. - Jenkins renovation: Abatement and selective removal work are underway; district staff said the plan reuses some mechanical…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat