Kenner council approves $90,700 change order for City Hall demolition

3796436 · June 6, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a $90,700 change order to the Pipe Works demolition contract after crews found unexpected foundations and a septic system while demolishing City Hall building A.

The Kenner City Council on June 5 approved Change Order No. 1 to the demolition contract for Kenner City Hall, increasing the agreement with Pipe Works Plumbing and Demolition LLC by $90,700 and adding 10 working days.

City staff (public works representative Mr. Gonzales) told the council that during demolition of Building A contractors encountered two different, unanticipated foundation plate levels. To properly expose piles the contractor had to remove additional concrete and excavate deeper than planned; the work also required additional sand to backfill the lower elevation. In addition, demolition revealed an old sewer/septic system that required removal. Those three issues—deeper foundation work, extra backfill and removal of a septic system—generated the change order amount.

The change order raises the contract total to $557,030 for the City Hall Building and Annex Building B demolition project (AE project no. 20‑22037B). Council approved the amendment by unanimous voice vote, 7–0, as recorded in the transcript.