Board approves modular building for Battleground Virtual Academy; district cites impact‑fee funding and winter move‑in

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved a contract to construct a modular building for Battleground Virtual Academy at the Prairie High School site. The district said impact‑fee revenue will pay construction costs and expected move‑in will be after the next winter break.

The Battle Ground School District Board of Directors voted 4–0 on May 27 to approve a contract for a modular classroom building for Battleground Virtual Academy (BGVA).

Facilities staff presented plans for a roughly 10,000‑square‑foot modular complex to sit north of the Prairie High School tennis courts and said the units will include teacher offices and small classrooms configured so each virtual‑program teacher has a private workspace. The district will fund construction with capital‑project impact fees collected from building permits; staff said those funds cannot be used for operations or personnel.

Presenting the contract, facilities staff said modular construction accelerates schedule and reduces weather exposure compared with conventional construction, but that factory production and a heavy barge schedule meant the district’s delivery window is in September and site setup will push actual BGVA move‑in to after the next winter break. “There are a lot of benefits to constructing modules for our district,” the presenter said, noting the building is “almost three times larger than where they’re at right now.”

Board members had procedural questions about unit design and confirmed impact fees pay only for capital work, not staff or programming. The board approved the contract after a motion; the vote was 4 in favor, 0 opposed.

Public comment included BGVA teachers who said on‑site administrative leadership and continuity matter to the program’s compliance and growth. Several BGVA staff urged the board not to remove BGVA’s principal, saying the position supports special‑education IEP work, weekly contact and program accreditation.

Ending: The district will proceed with the modular contract; staff estimated on‑site construction and fit‑out will be complete for a post‑Christmas break opening and said they will return with schedule updates.