Town approves $1.085 million of capital requests; Cromwell schools outline 19-project plan and middle school move timeline
Summary
The town approved $1,085,000 in capital requests tied to school projects; district officials said 19 projects totaling about $2.8 million were advanced and outlined packing and move dates for the new middle school.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Cromwell town leaders approved $1,085,000 in capital requests that the school district had submitted, district officials said at the Board of Education meeting. The town and district are coordinating on a slate of 19 projects the superintendent described as totaling about $2.8 million.
Claudio (last name per transcript: Bozzano) told the board the original package included 20 projects; one item'the high school LED project, estimated at about $670,000'was moved back one year to allow capacity to complete the others. "We started out with 20 projects totaling about $2,800,000. Of all those ... all those projects have been approved by the town council. We moved that (the LED high-school) back 1 year," Claudio said.
He said work scoped for WIS (the middle-school facility referenced in materials) totals about $400,000 and includes interior, exterior and controls work. The town will perform three of the projects with town crews; the district will cover materials costs within the approved amount.
Officials also said the town has applied for state bonding support for the track through Senator Lesser's office and asked the school board for help coordinating a writing campaign in support.
Separately, the district updated the board on the schedule for moving into the new middle school: teachers and staff will receive packing materials the week ending March 27 and training on March 26; the school will close June 13 for packing, with central office remaining open about one to two weeks longer. The district said movers will relocate materials on June 27 and the building becomes operational afterward; administrators noted logistical details remain to be finalized.
Board members and administrators thanked the town for the collaboration and said progress is the result of extended committee work with town staff and the mayor's office.
Ending: The approvals and coordinated plan clear the way for a large set of facility upgrades and the new middle school move; the school administration will return to the board with implementation details and any required follow-up for town-level approvals.