Board hears quarterly capital construction update: jail expansion, Pathways facility, HHS lobby and new operations center among projects under way
Summary
Coconino County departments briefed the Board of Supervisors on capital projects in design or construction, including the jail medical/intake addition, Pathways-to-Community facility, HHS lobby and a planned county operations center and Public Works storage facility.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Coconino County department leaders on June 3 presented a quarterly capital construction update to the Board of Supervisors covering projects in design, closeout and construction across multiple county departments.
Sheriff's Office: Sheriff Adam Axline (identified in the meeting as the lead presenter from the sheriff’s office) said the county is moving forward on a two‑part jail improvement that includes a new medical unit addition (about 15,000 square feet of medical and exam/infirmary space) and an intake/transfer and release renovation to separate intake and release flows for safety. The jail project budgeted $20 million combines $10 million from jail district reserves and $10 million from a bond issuance. Construction was described as beginning imminently and scheduled to end in April 2027.
Facilities/Pathways: Jeff Stein, senior construction manager in Facilities Management, described a two‑phase Pathways to Community project that repurposes space inside the county facility and adds about 1,500 square feet of new construction for behavioral health and re‑entry services. Phase 1 (tenant improvements) was completed in spring 2024; phase 2 construction is finishing and staff and furniture moves are expected imminently. Funding included opioid settlement grants and job‑order contract work.
Health and Human Services: Facilities staff described an HHS lobby renovation and a 3,000‑square‑foot youth behavioral center retrofit within the King Street building. The combined HHS scope is budgeted at $3.3 million, with design and permitting underway and construction planned for fall 2025 into spring 2026. The plan also anticipates moving Emergency Management/Operations Center functions during construction and ultimately consolidating an EOC at the Sheep Hill public works campus.
Operations center and Public Works storage building: Facilities and Public Works staff jointly presented a proposed new operations center (about 9,000 square feet) at the Sheep Hill campus to house emergency management and flood control functions. The concept budget range is $4.5–$5.5 million; staff is targeting a fall 2025 hard‑bid and a construction window of about a year. Public Works will also construct a new vehicle/storage building and multiuse “ready rooms” for maintenance crews; the two projects will be bid and built to leverage economies of scale.
Tusayan Service Center planning: County staff also updated the board on a planned multi‑departmental service center in Tuba City (referred in the meeting as the Tuba City regional service center or “Tribal/Navajo area service center”), using a congressional appropriation application and county contributions; staff said USDA funding review was pending and the county has resubmitted for additional federal funds for future years.
Ending: Staff said they will bring quarterly updates on these projects to the board and coordinate timing as budgeted work moves to construction and occupancy.