Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Pud Deseret Metals topic
No spam. Unsubscribe anytime.
Grantsville council approves Deseret Metals PUD with conditions on park, sewer and road work
Summary
The Grantsville City Council voted Thursday to approve a planned-unit development (PUD) and an associated master development agreement for the Deseret/Desert Metals project, attaching conditions on park construction, sewer connections and road work required by UDOT.
Get email alerts on the Pud Deseret Metals topic
No spam. Unsubscribe anytime.
The Grantsville City Council voted Thursday to approve a planned-unit development (PUD) and an associated master development agreement for the Deseret/Desert Metals project after public comment and negotiation on conditions, including park construction, sewer capacity and road alignment.
The council's action followed hours of discussion, a public-comment period and a preceding training on conditional-use law. Wade Budge, attorney for the Romney Group (the applicant), told the council the developer had revised the plan multiple times and said the submission included a west-side park, relocated collector road and agreed setbacks. "Romneys aren't going anywhere," Budge said, adding the company was willing to cap total units and dedicate road and park land to the city.
City staff and the developer agreed to conditions the council added to the approval. Those conditions, incorporated into the master development agreement, include: installation of gravity sewer lines to connect into existing infrastructure as described in the city's water memo; construction of deceleration and acceleration lanes and other turn-lane work required by the Utah Department of Transportation (UDOT) for SR-112; coordination between the city, the developer and UDOT on the SR-112 cross-section and timing for improvements; dedication of a 10-acre park (with a retention area no deeper than 3 feet) to the city; a requirement that the park design receive city-council approval; installation of solid fencing along the project's eastern boundary adjacent to industrial property and along the edges adjacent to SR-112 (with maintenance assigned to the HOA); and front-yard landscaping completed before issuance of certificates of occupancy.
Robert Rizzell, the city engineer, told the council the wastewater system had remaining capacity of about 2,000 ERCs (equivalent residential connections) and that the new treatment plant the city expects to construct would likely take about three years to complete. "We've got the remaining capacity of 2,000 ERCs in the treatment plant... it's gonna take at least we think three years to construct that new treatment plant," Rizzell said, noting staff would confirm legal details with counsel about moratoria and permit timing.
Several residents raised procedural and substantive concerns during public comment. One commenter urged careful compliance with Utah Code 10-3-508 and 52-4-202 when reconsidering earlier council actions; another warned the city about potential liability if a development agreement vests rights before infrastructure is available. Multiple speakers pressed the council on school capacity, noting estimates that several hundred homes could generate enough students to require a new school; both attorneys and staff responded that school siting and construction are decisions for the separate school district and that cities have limited authority to impose school-related exactions.
Traffic and road alignment were major themes. Residents asked that the project's proposed collector align with the approved 20Wells project to the south so intersections do not create offset crossings on SR-112; councilmembers and the developer said UDOT controls intersection spacing and the developer must secure UDOT approvals. The council added language requiring coordination with the 20Wells development and UDOT on road alignment and timing.
Council members also debated the timing of park construction. The PUD and MDA include a provision tying park construction to buildout thresholds; members discussed whether the park must be at least 50% complete or 70% complete before additional residential buildout proceeds. The final conditions, adopted as part of the development agreement, require the park to be dedicated to the city, built to a value at least equivalent to park impact fees collected for the project, and the park design to be approved by the city council. Council and staff also confirmed that some preliminary and final plats may be approved at staff level depending on the phase and that any changes to the approved PUD elements would return for council review as required by code and the development agreement.
The council vote approved the PUD and the master development agreement with the listed conditions. A roll-call vote was taken; the acting council recorded four ayes and the motion carried. City attorney Tyson Barker and other staff flagged an error in earlier meeting minutes showing a fifth council member as voting at a prior meeting when that member had actually been absent; staff said the minutes issue would be corrected on a future agenda.
Mayor and council members who spoke urged continued coordination among the city, UDOT and neighboring developers to ensure intersections align, to limit traffic impacts and to protect public safety during construction. Budge said the Romney Group would record the agreement and move forward under the terms agreed with the city.
The council also approved the master development agreement by motion and recorded the same conditions in that agreement, as part of the same evening's actions.
