Weber County staff tables East Estates subdivision over drainage, frontage concerns
Summary
Weber County staff and the applicant agreed to table final approval for LVBO11624 (East Estates) so the developer can confirm drainage pipe sizing and whether frontage ditch filling must be completed now or deferred until later development.
Get email alerts on the Subdivision Planning topic
No spam. Unsubscribe anytime.
Weber County staff and the applicant on March 6, 2024, agreed to table final approval of LVBO11624, a proposed two-lot residential subdivision (East Estates), after the developer raised unresolved engineering questions about storm drain pipe sizing and whether an adjacent frontage ditch must be filled now or at a later development stage.
County staff presenter Mr. Labarino said the owner had submitted materials needed for final approval, including civil drawings and will-serve letters, and that annexation into the Central Reserve 0 District would be required before the plat could move forward. Mr. Labarino also noted there were “a few comments that will be taken care of from the revised subdivision plan and a couple small changes to the civil plans.”
The developer’s representative (identified in the record as Felix) told the commission they had two outstanding due-diligence items to verify with county engineering. First, engineering had requested a 48-inch drainage pipe at the project location; the developer asked the county to verify that requirement, noting a nearby section of the same ditch roughly 1,000 feet upstream had a 36-inch pipe. Second, the developer proposed to cover (pipe over) 100 feet of the ditch frontage adjacent to the proposed road and defer filling the remainder of the frontage until any future development of the adjoining property, while engineering had requested the entire frontage be filled now.
Mr. Labarino asked whether the applicant wanted the item tabled until those issues were resolved. Felix replied they would like to verify the pipe-sizing and frontage-fill questions with engineering and asked for the item to be tabled. Mr. Labarino said, “If that's the case, we would like to table that out. Alright. Well, then I will table this item, give you time to get with engineering and the request ends up.”
The record shows no formal vote tally for the tabling; the action was recorded as tabled so staff and the applicant could resolve the engineering questions. The staff report language and other standard conditions (monument and improvement agreement; financial guarantee of subsequent improvements) remain applicable when the applicant returns the item to the agenda.
Clarifying details recorded in the meeting included the developer's description of the two main outstanding technical issues (48-inch pipe request vs. a 36-inch pipe observed upstream; the developer offered to cover 100 feet of frontage now and defer the remainder). The owner acknowledged they understood annexation into Central Reserve 0 District would be required before plat recordation. The meeting did not include a scheduled date for returning the item to a future agenda.
The tabling preserves the applicant’s ability to resolve engineering comments and to adjust the final plat accordingly; no final approvals were granted for LVBO11624 on March 6.