Board authorizes early procurement packages with PCL for office space and solids handling upgrades

2626446 · February 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved two early guaranteed-maximum-price packages with PCL Construction for Phase 2 space improvements and solids-handling upgrades at the Allen Water Treatment Plant; total early procurement authorization is $854,637.

The Englewood City Utilities Board authorized early procurement under two Construction Manager/General Contractor (CMGC) agreements with PCL Construction to advance a Phase 2 office-space project and a solids-handling improvements project at the Allen Water Treatment Plant.

Sarah (last name not specified) explained the delivery method: PCL was engaged under a professional services agreement during design to provide constructability input and cost certainty. Staff recommended early procurement packages so long-lead materials and fabricated components are ordered to…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans