RMA updates 365 Tollway construction, approves change orders and testing-contract amendments
Summary
Staff reported progress on the 365 Tollway and associated projects; the board approved change orders and contract amendments including savings on a wetland mitigation contract, a remobilization payment to a contractor after an irrigation-district stop-work order, and reassignment of construction testing work to Terracon.
The Hidalgo County Regional Mobility Authority received construction updates for the 365 Tollway and approved a series of project contract actions, including a deductive change order on a wetland mitigation contract, additional funding for construction inspection and materials testing, and a $150,000 payment to the tollway general contractor for remobilization after an irrigation district issued a stop-work order.
Ramon Navarro, chief construction engineer for the RMA, told the board the Grama Henlo wetland mitigation project's completion schedule was revised but remains on track; staff recommended and the board approved Change Order No. 1 to reduce the contract by $187,915.96 after a consultant redesign found efficiencies. Navarro also reported the wetland contractor is about 42% complete and that the revised substantial-completion date is Feb. 18, 2025, with final completion March 20, 2025.
Staff presented multiple procurement and inspection items tied to the large construction program.…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat