Council approves pipeline modernization amendments to clear streets and require coordination on traffic impacts
Summary
City Council approved three amending motions (14a, 14c and 14d) concerning pipeline modernization and related work near Baldwin Hills; the motions ask for expedited pipe replacement, franchise coordination (noting a new franchise owner named in the record), and interdepartmental coordination to limit traffic impacts along La Cienega and Rodeo.
Get email alerts on the Infrastructure Pipelines topic
No spam. Unsubscribe anytime.
The Los Angeles City Council on July 20 approved a set of amending motions related to pipeline modernization and street resurfacing in the area between the Pico corridor and Baldwin Hills, voting 11-0 to adopt motions 14a, 14c and 14d.
Councilmember Holden described the item as a preventative retrofit of pipeline infrastructure that currently carries fuel from the Pico area toward Baldwin Hills. Holden said the existing pipes are more than 50 years old and that modernization is intended to prevent failures that could lead to fires or explosions. The amended measure would expedite replacement or repair so that street resurfacing and other follow-on work are not delayed.
Holden also said a different company โ identified in the meeting as Stalker Oil โ will be the new franchise owner of the pipeline once the work moves forward. Councilmember Ridley-Thomas and Councilmember Padilla introduced or sponsored coordination language to ensure city departments consider traffic impacts on La Cienega and Rodeo and to coordinate with the Bureau of Street Services and the Board of Public Works.
Ridley-Thomas specifically called for departments to be fully aware of and to mitigate traffic impacts to residents and businesses; he said coordination would help align the proposed pipeline work with the ESYS project and other street projects. The council recorded an 11-0 vote to approve the amending motions together.
The motions instruct city departments to coordinate construction and traffic control planning, and to expedite necessary franchise or franchise-transfer steps so pipeline work and street resurfacing can proceed with minimized disruption. Specific implementation details and schedules were not provided at the dais and will be handled by the implementing departments.