Board approves $300,000 contingency increase for William Blount CTE renovation project

2522268 · March 7, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a request to add $300,000 to the contingency fund for the William Blount CTE renovation project after district maintenance described unforeseen site and owner-requested changes that consumed most of the prior contingency.

The Blount County Board of Education on a roll-call vote approved a request to increase the contingency for the William Blount CTE renovation project by $300,000.

Maintenance and project staff said the project is transitioning from phase 1 to phase 2 and that change orders and owner requests have reduced the previously authorized contingency to about $44,000. Maintenance director (referred to in the meeting as Mr. Dukes) told the board the $300,000 request is to ensure work can continue through June 30 if additional change orders arise.

Why it matters: The contingency covers unexpected site conditions and owner-requested changes; without added contingency, work could pause or require emergency approvals. Mr. Dukes provided examples of major unplanned or owner-requested items, including a fire lane added behind the CTE area, rerouting of a fire and domestic water line when site utilities were not where plans called for them, power-line reroutes to accommodate furniture and classroom arrangements, extension of a delivery road for the culinary arts area at an instructor's request, and exterior cladding work to improve aesthetics on installed columns.

Financial details cited at the meeting: Mr. Dukes said the board previously authorized $300,000 in contingency earlier in the fiscal year and that $44,000 remained. He said the district will present a report to the county commission documenting expenditures since the prior authorization. He also stated that at fiscal year-end any unused contingency will return to the general fund balance; in his words, "At the end of this fiscal year, any unused amounts will go back into the $1.77 general fund, the fund balance of that." The board discussed value engineering and noted one change produced a $70,000 credit after selecting a different ceiling tile.

Board action: Trustees voted by roll call to approve the additional $300,000 contingency. Board members asked for examples and for transparency on how contingency funds were spent; the maintenance staff committed to reporting expenditures to the commission.

Next steps: Administration will present a detailed accounting to the commission of contingency uses since July and, if needed, request a similar authorization for the next fiscal year.