Committee selects low bid to repair 1924 armory wall; Brickworks low bidder at about $245,000
Summary
Facilities presented a structural assessment and a bid package for repairs to the armory wall; committee approved moving forward with the lowest bid and contingency for concealed conditions.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Pat, Facilities, presented a structural assessment of the armory wall, constructed in the 1920s and noted the need for mortar repair, stabilization of loose stone and brick, and tuckpointing.
Pat said Restore Consulting completed the structural assessment and provided cost estimates; the county developed a bid package and received four bids. Pat reported Brickworks submitted the lowest bid and recommended that the county use capital-improvements funds to pay for the work.
Commissioners asked about the variation between bids and whether the low bid covered the full scope. Pat said the higher bids reflected larger firms' pricing and that the scope of work was based on the Restore Consulting specifications; the facilities project manager recommended awarding the work to the low bidder with a 5% contingency for concealed conditions and alternate items that could be added once work begins.
A commissioner requested a post-project accounting of any contingency dollars used; Pat agreed to return with a contingency-use report after project completion. The committee voted unanimously to support moving forward with the low bidder and to use capital-improvement funds to pay for construction.