Rec and Park, Port report near‑completion of 2012 Clean & Safe Neighborhood Parks bond projects
Summary
Recreation and Park reported 99% of 2012 bond funds spent or encumbered with two active projects—Stern Grove playground and McLaren Trails—moving to completion; the Port said Agua Vista Park and Pier 27 public art remain in later stages tied to other construction schedules.
Stacy Bradley, director of capital and planning at Recreation and Park, and Simon Betzalel, project manager in the Port of San Francisco’s engineering division, updated the committee on the 2012 Clean and Safe Neighborhood Parks GO bond program.
Bradley said Rec and Park has spent or encumbered 99% of the 2012 bond funds, delivered 80 completed…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat