Council approves change orders as power work, geotech questions continue on Parkway project
Summary
Toquerville City Council approved two change orders tied to the Tokrill Parkway project and received updates on power-line work and geotechnical reviews; UDOT geotech sign-off still required before contractor work resumes on a north slope repair.
Toquerville City Council approved two change orders tied to the Tokrill Parkway project and heard project updates that say Rocky Mountain Power expects to energize new lines by March 17, but the city and UDOT geotechnical reviewers still have questions to resolve before some construction resumes.
The council voted to approve change order No. 15 (temporary north/high-end access) in an amount not to exceed $130,000. The motion passed on a roll-call vote. Council also approved change order No. 17 to relocate power vaults out of the clear zone; the city’s share was approved up to the amount proposed by staff (the city will split a larger total cost with the developer). Both items were presented as project costs and not charged to…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat