Council approves $63,890 change order for Laguna Boulevard project and budget transfer
Summary
Council approved change order number 2 for the Laguna Boulevard project in the amount of $63,890.25, bringing total change order percentage to 22.36%, and approved a budget transfer of $55,782 to pay for the change order.
Get email alerts on the Public Works Change Order topic
No spam. Unsubscribe anytime.
The City Council approved change order number 2 for the Laguna Boulevard (LB LVD‑PW2401) construction project in the amount of $63,890.25 and authorized a $55,782 budget transfer to pay for the change order.
Public Works staff described the work involved as adjustments to paving and curb areas, including some instances where concrete will replace asphalt and some anticipated deduct change orders where credit will be returned for removed items. Assistant Public Works Director John Wilson said some paving areas were swapped from asphalt to concrete and that the city expects a subsequent deduct change order in other locations.
Council approved the change order and the associated budget transfer. Staff said in-house crews will handle striping work and that some striping was scheduled to start the following day.