San Jose Clean Energy to amend battery-storage contract after transmission delays; price reduced, dates moved
Summary
San Jose Clean Energy won council approval to amend its contract with NextEra’s Yellow Pine Solar 3 battery project after transmission upgrades delayed commercial operation dates; the amendment reduces price and extends commercial online dates to meet CPUC resource adequacy deadlines.
The San Jose City Council on March 4 authorized staff to amend an existing power purchase and storage services agreement with Yellow Pine Solar 3, a battery storage project developed by NextEra Energy Resources, to reflect multi-year transmission delays and a reduced fixed price over the contract term.
City energy staff said the amendment responds to transmission upgrades outside the developer’s control. The contract originally assumed commercial operation of the storage and tolling product in June 2025, but the upgrades pushed the tolling (charge/discharge) date…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat