Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Procurement Furnishings topic
No spam. Unsubscribe anytime.
County staff lay out furniture options as tariffs put Global Furnishings prices in flux
Summary
Project staff told commissioners tariffs may raise the cost of a previously selected Global Furnishings package; staff outlined three price/lead-time options for roughly 65 desks and sought direction ahead of an April 1 order target.
Get email alerts on the Procurement Furnishings topic
No spam. Unsubscribe anytime.
Kootenai County project staff told the Board of County Commissioners on March 4 that new tariff guidance could increase the price of a previously selected furniture package and presented three options for outfitting the justice building and associated offices.
Project staff said Global Furnishings—chosen during earlier procurement discussions—has a U.S. corporate address in New Jersey but sources some manufacturing from Canada; the vendor warned the county and its contract-design representative that new tariff rules may require additional charges on upcoming orders. Staff outlined three options: continue with Global (previously quoted at about $1,300 per typical desk but potentially subject to added tariff charges), switch to U.S.-based manufacturers (Herman Miller, OFS, Kentucky Office Furniture) with typical desks roughly $1,800 each, or buy an off-the-shelf import package from an importer identified in the memorandum (referred to in the discussion as HBC) at about $999 per typical desk.
Project staff said lead times differ: Global’s quoted lead time is roughly eight weeks; the importer’s stock option could ship in two to four weeks. Commissioners and staff discussed durability and edge treatment as factors that affect long-term value; staff suggested testing samples and confirming whether higher-priced U.S. options are fully manufactured in the United States. The county expects to buy roughly 65 desks; staff said choosing the $999 option would save roughly $42,000 compared with the higher-priced options under the scenario discussed.
Commissioners asked for time to confirm what U.S.-branded options actually manufacture domestically and for staff to return with clarified options before a target order date. Project staff said the target order date is April 1 to meet an eight-week delivery window if using Global. No formal procurement decision or vote was recorded at the March 4 status meeting.
Public comment at the end of the meeting urged the county to seek a volume discount and proposed using license-plate readers to improve collection of boat-launch fees elsewhere on county property; those comments were not directly connected to the furniture procurement but were voiced during the public comment period.

