Council authorizes additional work on 8 Mile water main after unrecorded utilities, raising project cost to about $794,000

2484307 · March 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The city approved additional costs for the 8 Mile water main project after discovery of an existing gas main and unrecorded cast-iron water main sections, increasing the project from about $601,000 (with contingency) toward an estimated $794,000 total.

The St. Clair Shores City Council approved additional scope and associated costs for the 8 Mile water main project after field discoveries revealed unrecorded utilities and older pipe that required replacement. The council voted 7-0 to accept the change orders and additional work described by city engineering staff.

City engineer Mike Freckleton summarized three key issues that drove the cost increase: (1) pre-construction locating revealed a gas main running over the…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans