Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Street Reconstruction topic

No spam. Unsubscribe anytime.

Council awards $1.687 million local streets reconstruction contract to Mark Anthony Contracting

2484307 · March 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Mark Anthony Contracting won the low bid and the council voted 7-0 to award the 2025 local streets reconstruction package, which covers short sections of Wood, Ursuline, Princeton and Greater Mac.

The City Council on March 3 awarded the 2025 local street reconstruction package to Mark Anthony Contracting for $1,687,005.65, including a 10% contingency, authorizing repairs on short segments of Wood, Ursuline, Princeton and Greater Mac.

City engineering staff summarized the four work locations: small sections of Wood and Ursuline (Stevens to Blackburn), Princeton (from 10 Mile to the dead end near the elementary school; the council noted this will impact about four houses), and Greater Mac (11 Mile to Gordon). Staff said Mark Anthony was the low bidder from a competitive field of 11 bidders; the city expects contractors to start after weather permits.

Council members discussed coordination and construction sequencing across the multiple, geographically scattered sites. Councilmember Cameron (dais comment) reminded staff to ensure contractors do not stage concrete removal across all locations simultaneously, to preserve access to neighborhoods; staff committed to reviewing mix designs and on-site batching to avoid concrete scaling and flaking. Councilmember Vitale asked about tree impacts; staff said only the Greater Mac segment was likely to require tree removals and that staff would provide a tree impact count and proposed replacements.

The motion to award the contract to Mark Anthony Contracting, moved by Councilmember Rubello and seconded by Councilmember Roussy, passed 7-0.

Why it matters: the award funds multiple local reconstruction projects totaling mid-seven figures; council discussion addressed construction coordination, protection of neighborhood access, and tree-canopy concerns.

Next steps: staff will finalize contract administration, provide tree-impact details and replacement plans for Greater Mac, review concrete mix designs with the contractor, and schedule field work as weather permits.