San Mateo awards Central Park playground construction contract after value-engineering; $10,000 donation accepted
Summary
Council awarded an $8.49 million construction contract (with a $1.27 million contingency) to Suarez & Munoz Construction for Central Park playground improvements and accepted a $10,000 donation from the Parks & Recreation Foundation in honor of former director Sheila Kansian.
Get email alerts on the Parks And Rec Playground topic
No spam. Unsubscribe anytime.
The San Mateo City Council on March 3 approved awarding a construction contract for the Central Park Playground Improvements project and accepted a $10,000 donation from the San Mateo Parks and Recreation Foundation in honor of former director Sheila Kansian.
King Leong, senior project manager in the Parks and Recreation Department, and Director Joanne Magrini briefed the council on a multi-year planning process that began with a 2014 master plan and included environmental review and community workshops. The project’s original construction bids exceeded available funding; staff, the design team (RRM Design Group) and the low bidder negotiated value-engineering changes that reduced the construction cost from an initial bid of about $11.5 million to a contract base of $8,485,784.
Council approved a contingency of $1,272,868 for a total project authorization of $9,758,652. Staff described value-engineering steps that preserved the Adventure Village playground theme while reducing cost: relocating the 2–5‑year-old play area to avoid work in a high-maintenance zone near heritage trees, lowering an elevated play platform to grade, replacing a more elaborate picnic shelter with a simpler hip-roof shelter, and selecting a prefabricated turnkey restroom building to speed installation and reduce on-site labor. The surfacing for play areas will use engineered wood fiber, which staff said provides accessible surfacing at lower cost than poured-in-place rubber or artificial turf.
The council asked about accessibility and fencing; staff confirmed inclusive play elements and that the 2–5 play area will be enclosed by fencing and that historic park fencing remains along El Camino Real. Council members praised the cross-department project team for preserving design integrity while meeting budget constraints.
A motion to accept the $10,000 donation and to award the contract to Suarez and Munoz Construction in the base amount of $8,485,784 with a contingency of $1,272,868 passed 4-0. The resolution accepting the donation and contract authorization allows the parks director to execute the contract and approve change orders within the contingency.
Staff said a groundbreaking will follow council action and that a communications plan will inform neighbors and park users during construction.