Kings Local: High‑school site work advances; Columbia addition on track for Oct. 1 turnover
Summary
HGC Construction reported progress on the Kings Local district’s Columbia addition and the new high‑school site, including completed HVAC and playground work at Columbia and multiple foundation bid packages for the high school that came in under budget.
HGC Construction told the Kings Local Board of Education on Tuesday that work on the Columbia addition is substantially complete for summer‑work items and the district’s new high‑school site has advanced through early site grading and foundation bid selection.
The update, presented by Bill Brownback and a colleague identified as Dave from HGC Construction, said crews finished a summer chiller replacement, corridor ceiling and utility upgrades, new sprinkler and electrical conduit installations and a relocated playground at Columbia. “We said we'd do it in 9 months, and I'm standing here happy to report that we are gonna meet that date and turn that thing over in that time frame,” Brownback said. He told the board the contractor expects to “turn over the first piece of this whole program back over to the King's community” by Oct. 1.
The…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat