Lingo Construction reports steady progress on Piedmont bond projects; science-classroom tops delayed
Summary
Jacob Lingo of Lingo Construction told the Piedmont School Board the district’s bond-funded building projects are advancing despite persistent rain, and that masonry, utilities and shelter work are on the near-term critical path.
Jacob Lingo of Lingo Construction told the Piedmont School Board the district’s bond-funded building projects are advancing despite persistent rain, and that masonry, utilities and shelter work are on the near-term critical path.
Lingo said masonry is rising in Block 2 of the new intermediate school and that the precast storm shelter — which will serve as the gymnasium — is fully erected, though topping slabs and finishing remain to be done. He said the next critical work is a slab-on-grade pour for Block 3, scheduled for the coming week but subject to further rain delays.
The update matters because paving of an orange-shaded portion of the intermediate site…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat