Council awards Courier Street water-main replacement to Absolute Quality Inc. for $510,056.50

5810420 · June 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council accepted the low bid from Absolute Quality Inc. of Brownstown, Michigan, for the Courier Street water main removal and replacement project for $510,056.50, with work funded from the water and sewer fund and contractual completion slated for Aug. 25, before school starts.

The Wayne City Council voted June 17 to award the 2025 Courier Street water-main removal and replacement project to Absolute Quality Incorporated of Brownstown, Michigan, for the low bid of $510,056.50. Funding for the project will come from the city's water and sewer fund.

City staff said the project was designed in-house by the city's engineering staff in coordination with the Department of Public Works and covers the full segment of Courier Street from Moore Street to William Street, just west of Wayne Road. "Construction is slated to be completed contractually by August 25 prior to school starting," the staff presenter said, noting the contractor must provide bonds and is expected to start work within two to three weeks after approvals.

Bids received were read into the record; Absolute Quality Inc. submitted the low bid of $510,056.50, followed by Spring Line Excavation ($532,742), Main Street Contracting ($533,900), Adia Concrete ($595,150.50) and others. Staff stated the low bid is within 10% of the project's engineer's estimate and said references for the low bidder were checked by the city's engineer, Kevin Hardy.

Why it matters: The project includes both water-main replacement and full roadway reconstruction for the Courier Street corridor, and the August completion target is intended to avoid disruption when schools reopen.

Council action and conditions: The council moved and approved the bid award to Absolute Quality Inc. Staff said the contractor must provide required bonds and meet the contract schedule; staff will monitor progress and adherence to the contract documents.

Ending: The motion to award the contract carried by voice vote. Staff said they will return with routine contract documents and begin pre-construction coordination.