Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Sewer Spill Turkey Creek topic

No spam. Unsubscribe anytime.

Palm Bay reports 1.16 million gallons released after Turkey Creek sewer main break; cleanup, testing ongoing

5511306 · July 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff told the council the June Claremont force-main break released about 2.41 million gallons of sewage, of which roughly 1.25 million gallons were recovered; restoration and water-quality testing continue and the city estimates repair and cleanup costs of about $1.124 million.

City of Palm Bay utilities staff updated the council on a June force-main break near 1050 Claremont that released an estimated 2,410,000 gallons of sewerage into the Turkey Creek watershed, with about 1,250,000 gallons recovered and roughly 1,160,000 gallons released to the environment.

Utilities Director Gabriel Boden told council crews first responded after the break was reported June 8, and that contractors were called in when crews found a large breach in a 20-inch main. The bypass was restored to the treatment plant the next day, Boden said. "We recovered approximately 1,250,000 gallons," he said at the presentation.

The city deployed three turbidity barriers, removed affected soils from nearby storm ponds and skimmed solids from the creek. Staff reported removing about 702 cubic yards of contaminated soil and skimming roughly 56,000 gallons of water mixed with solids. The city also removed stained asphalt and expects road resurfacing to cost about $75,000.

Water-quality sampling was conducted in coordination with the Florida Department of Health and Florida Department of Environmental Protection. Staff said background Enterococcus counts were elevated in the watershed before the break, and that post-remediation samples show improvement; the city noted long-running monitoring by a regional marine research group.

City staff estimated direct repair and restoration costs at about $1,124,000. Boden said staff is investigating additional long-term measures including aeration and possible dredging, improving inventory of emergency bypass equipment, pipeline inspections for aging mains and cooperative agreements to speed response for rare, large items that contractors do not routinely stock.

Boden and others on the operations team named multiple staff and a private contractor, Cathcart, for field response work. Council members praised the response and asked staff to follow up on dredging feasibility, inspection technologies and timelines for remaining restoration work.

The city said it stands ready to provide the full sampling results and restoration updates to residents; additional outreach included door-to-door notifications, a public hotline, website banners and press releases.