The Millis School Building Committee reviewed revised floor and site plans July 9, including a shifted gym wall, updated bus/car circulation, parking changes and a plan to stake out the new building footprint on the campus to help the community visualize impacts to adjacent fields.

The Millis School Building Committee reviewed updated schematic floor plans and an updated site plan at its July 9 meeting, hearing that the most notable floor change is a gym wall moved inward and that work now is focused on detailing trades and engineering coordination.

Chris, the meeting presenter, told the committee, “This plan, the most notable difference is the gym moving, the gym wall on on this side moving inward. And so we've captured that now,” and said most near-term changes are coordination among mechanical, electrical and plumbing scopes as the team prepares the cost-estimate set to issue next week.

Why it matters: committee members raised concerns about how the addition sits next to existing playing fields, pedestrian circulation and emergency access. Jim said the committee should stake out the proposed footprint “so we can at least get a sense of where this is gonna be,” arguing a physical stake will help the public understand how close the new building will be to the ball field and existing memorials.

Site changes and circulation The updated site plan removes the previously shown permeable asphalt, adds an outdoor learning courtyard and expands a parking area. The design team shifted the bus circulation to run through a dedicated bus lane with a separate car drop-off loop; the plan anticipates some parent vehicles may also use the loop depending on operations. The design team added a small landscaped (green) island in the middle of the lot as part of stormwater mitigation discussions with civil and landscape consultants.

Committee members flagged operational questions the traffic engineers should answer before pricing: how many parent vehicles can queue without blocking the bus exit and whether a hatched “do not block” zone will be needed. The team said they will run auto-turn and circulation overlays with the fire department; preliminary analysis indicates apparatus can access the building but may need to back out of a dead-end area. The design team noted the building will be fully sprinklered, which factors into fire department acceptance of some dead-end access conditions.

Topography, retaining walls and med-flight access Presenters and committee members confirmed the site has grade differences near the ball field: the finished floor elevation was reported around 174.5, the bottom of a nearby stair at about 172.1 (roughly a 2.5-foot drop), and at the largest differential a retaining wall about 5 feet high. The design team also reported that med‑flight (helicopter) needs — a roughly 40-foot clear radius — can still be accommodated in the proposed parking layout and recommended showing a dashed helicopter-radius symbol on future plans for reviewers.

Next steps and committee direction The committee asked for a high‑resolution PDF of the cost-estimate set and plans so members can read dimensions and elevations; the design team agreed to send the files. Committee volunteers offered to place a stake or stakes on the ground using dimensions the team will provide; the committee agreed this physical marking would help community presentations.

The design team reminded members the next phase is pricing: the cost‑estimate set goes to estimators next week and the committee will review numbers at an Aug. 13 meeting as the group prepares for town meeting votes and additional outreach.

Ending No formal motions were required on the site plan at the meeting; the committee directed staff to provide the high‑definition plans, to coordinate auto‑turns with the fire department and to supply corner points so members can stake at least one location on the field prior to community presentations.