Marion council approves project calendar, moves Sea Mar Trail Phase 5 toward construction

5419342 · July 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Marion City Council on July 17 approved the project calendar and related resolutions for the Sea Mar Trail Phase 5 project, awarding the low bid to PCI with a late start date of June 1, 2026, and liquidated damages set at $1,200 per day.

The Marion City Council on July 17 approved the project calendar and related resolutions for Sea Mar Trail Phase 5, which will extend the trail from the area near Menards south to Mount Calvary Cemetery.

City Engineer Shonner told the council the low bid came from PCI and the contract includes a late start date of June 1, 2026, although the contractor may start earlier if materials and pedestrian bridges are available. Shonner said the contract allows winter work and carries liquidated damages of $1,200 per day.

The action followed a public hearing in which no substantial opposition was recorded. Shonner opened the presentation by calling the segment “something to celebrate,” and noted Cedar Rapids crews will pour a small portion adjacent to a ditch that city crews will not perform.

Council members moved and seconded the project-calendar resolution package (Resolutions 32,475–32,476). The motion passed on voice vote.

The project funding and detailed construction schedule are in the contract documents; staff told the council the bid packet had been circulated to the Department of Transportation. The engineer said the contractor’s ability to obtain pedestrian bridges could allow an earlier start than the stated June 2026 date.

Next steps include formal contract execution with the low bidder and preconstruction coordination; staff said they will return to council with the fully executed contract and schedule as required by city procurement rules.