Design review commissioners defer mixed-use downtown project at 3150 Main to August for more street, bike, and crossing details
Summary
The commission deferred DRH24-00031, a mixed-use development at 3150 Main Street, to August 13 after staff and commissioners identified outstanding phasing, streetscape, pedestrian crossing, bicycle, and landscaping issues and the applicant requested additional time to work with ACHD, VRT and city staff.
Get email alerts on the Mixed Use Development topic
No spam. Unsubscribe anytime.
Boise's Design Review Commission voted on July 9 to defer DRH24-00031, a mixed-use development proposal at 3150 Main Street, to the commission's August 13 work session to allow the applicant to address multiple outstanding conditions and interagency coordination items.
Planning staff outlined a set of conditions carried forward from the project's original approval and a set of new items the applicant must resolve before construction permits would be issued. Required items include floodplain and river system approvals, vegetating disturbed but inactive areas, an enhanced pedestrian crossing connecting the Greenbelt and an adjacent school at Whitewater Park Boulevard, a more detailed phasing plan, planting plans (including removal of pear trees and artificial turf along the Greenbelt), final hardscape and streetscape designs, a solid-waste plan, bicycle-parking details and grading/drainage plans that comply with Public Works and ACHD standards.
Applicant Ryan Cutler (Alquist Development) said the team has worked with project partners, submitted exhibits to the Ada County Highway District (ACHD), and asked the commission to modify three conditions (noted in staff materials as c, h and n). The project team provided an ACHD email that indicated ACHD 'would not recommend' an enhanced crossing at the Whitewater Park Boulevard location shown in staff materials; staff said the condition as written allows the applicant to move forward without the crossing only if ACHD provides a written statement explicitly prohibiting it. The applicant also sought flexibility on corner-entry pedestrian connections and on streetscape/bike-lane configuration along Main Street, explaining the proposed layout would match nearby streetscape and bridge alignments and align the bike lane with the existing protected lane across the Main Street bridge.
Commissioners raised multiple concerns: one commissioner said the pedestrian crossing is 372 feet from the next crossing and nearly 900 feet from another, and favored retaining the crossing condition unless ACHD explicitly prohibits it; another commissioner criticized the overall site layout, saying the plan 'necks down' the plaza and does not produce the public spaces envisioned in earlier plans. Several commissioners supported keeping conditions requiring interagency coordination with ACHD, Valley Regional Transit (VRT) and the Central City Development Corporation (CCDC).
After discussion, Commissioner Aguilar moved to defer DRH24-00031 to the August 13 work session to allow the applicant to address additional items and the commission seconded; the motion passed unanimously. The deferment gives the applicant time to provide revised materials and specific responses to ACHD, VRT and city staff so conditions can be either satisfied or reworked before the project returns to the commission.
Key outstanding items flagged by staff include final streetscape drawings that specify any deviations from city streetscape standards, demonstration of bus-stop compliance with VRT requirements, finalized bicycle parking that meets code for specific uses, an unobstructed direct path from the public sidewalk at the intersection into the site or plaza, and complete grading and drainage that meets public-works requirements.