Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Transportation East Danville Connector topic

No spam. Unsubscribe anytime.

Boyle County, KYTC review east Danville connector options; no route selected

5215006 · July 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Kentucky Transportation Cabinet District 7 presented three route alternatives for an eastern Danville connector at a Boyle County Fiscal Court special call meeting July 7; court members did not select a route or approve funding and asked the Cabinet to gather further local input for the next highway plan.

Kentucky Transportation Cabinet District 7 officials presented reconnaissance findings and three route alternatives for an east-side connector around Danville at a Boyle County Fiscal Court special call meeting on July 7, but court members did not select a preferred alignment or authorize construction funding.

Kelly Baker, chief district engineer for KYTC District 7, told the court the project originated in a Danville small‑urban area study and later entered the state highway plan. Baker said the project had been assigned state funding when first added and that federal funds were later allocated, but the effort stalled after the corridor dropped out of the 2022 highway plan and the environmental documentation was never finished. "It originally had state funding assigned to the project…in 2018," Baker said, "and in 2020 it received federal dollars."

The Cabinet’s planning staff presented three alternatives identified on maps as Route A (closest to town), Route B (a tighter southern corridor) and Route C (a longer loop with more right‑of‑way flexibility). Engineers said traffic modeling indicates a connector could reduce congestion on Kentucky 34 (a two‑lane route KYTC reports is carrying more than 15,000 vehicles per day), but no single new road would solve the corridor’s network needs alone. "One cannot perform alone," the planner said, adding that the plan envisioned a network of improvements phased over many years.

Cost and constructability varied by alternative. KYTC staff gave a preliminary construction estimate in the range of tens of millions of dollars for the larger new‑alignment options (presentation notes and discussion cited a construction estimate near $43 million for a more southerly route and a figure of about $32 million cited by a city contractor for roughly 1.5 miles of an original alignment). KYTC emphasized those were preliminary estimates that do not yet include full right‑of‑way and utility relocation costs.

Court members and local speakers focused on two recurring concerns: (1) the connector’s potential to remove or damage established local businesses and newly planned private investment, and (2) how the project would compete with other county priorities for limited state and federal highway funds. Magistrate (long‑serving) members warned that routing a major new road through parcels now under active private development could imperil projects that local officials and private investors have already committed to.

Magistrate [name not specified] said the court had prioritized improvements to Kentucky 52 after discussing safety fixes there, and that the connector’s earlier inclusion in the highway plan had at one point pushed 52 to a lower priority. Several magistrates urged KYTC to consider alternatives that reuse or upgrade existing routes (for example, improvements to Ghost Pike, US‑150 and portions of KY‑34) rather than relying solely on new alignment(s).

Landowners and residents spoke during the meeting. Dan Campbell, registered agent for LME Holdings (Luca Mariano), said his group owns the majority of the property in the corridor and that landowners were not always notified of earlier meetings; he also said investors were committed to completing a large tourism and distillery project on the property. "There are investors coming in to complete that project in its entirety," Campbell said. Diane Pendergraft, who said she lives adjacent to the distillery site, said she was concerned about impacts to a long‑standing family business if a road cut through that area.

KYTC staff said Alternatives 2 and 3 used a magenta‑zoned corridor that had been reserved for a future roadway, while other alternatives would require more new right‑of‑way acquisition and potentially higher construction costs and environmental review. Because the project previously received federal funds, KYTC noted it would need to complete environmental documentation and demonstrate fiscal reasonableness to federal reviewers before the funds could be spent.

No formal action to select an alignment or to endorse a single alternative occurred at the meeting. KYTC told the court it will continue collecting local feedback as it prepares recommendations for the next biennial highway plan; the Cabinet described the July 7 session as a fact‑gathering and informational meeting for magistrates and local officials. The court did adopt only a routine motion to adjourn: Magistrate Ellis moved, Magistrate Kellen seconded, and the motion carried by voice vote.

The discussion left several follow‑up items that the court and KYTC signaled they would pursue, including more targeted outreach to landowners in the corridor, additional review of using or upgrading existing roads as lower‑cost alternatives, and completion of the environmental documentation if federal funds are to be pursued. KYTC staff repeatedly warned the court that large‑scale connector and bypass projects are multi‑decade efforts and that competing statewide priorities mean funding for multiple large projects in the same area is unlikely to appear simultaneously.

Votes at a glance: The only recorded formal vote at the special call meeting was on adjournment. Magistrate Ellis moved to adjourn, Magistrate Kellen seconded; the court voted by voice (ayes) and adjourned.

Context: The court and KYTC characterized the east Danville connector as part of a long‑running series of studies dating to the 1970s and formalized in a 2014 small‑urban area study and the 2018 highway plan. KYTC said the corridor remains a candidate for future highway plans but that no final environmental determination or right‑of‑way acquisition has been completed. Local economic development interests at the meeting emphasized a currently active private distillery and proposed residential developments that court members said would be jeopardized by certain alignments.

— Reporting by Boyle County Fiscal Court meeting transcript; KYTC District 7 presentation excerpts and public comment were used as the primary sources for this article.