Construction program update: Miller, CHS and other projects move toward fall milestones, district says
Summary
A Jacobs project manager and district staff gave a quarterly status report on major construction and capital projects. Work on the Miller project is underway with some schedule adjustments; air handlers, elevators and other building systems were discussed and state permitting and bid timelines were outlined for upcoming work.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The district's capital-program manager and a Jacobs project manager presented a quarterly update on major construction projects funded by prior bond authorizations and capital budgets.
Presenters said the Miller project has completed initial construction submissions and is under state review; the team estimated that 75% to 80% of documentation points had been submitted in the first pass. Air-handler supply chain issues were noted as a near-term risk, but speakers said shipments were expected within weeks. At one high-school site, the team described a flooring correction effort, repainting and finishing work and said the building is substantially complete except for mechanical items such as boiler pumps that remain on order.
Elevators, turf and asphalt timelines Presenters said elevator work at DHS and Park sites has been challenging; crews are working to complete elevator work shifted to close to the start of school, and principals were coordinating contingencies. At one site the asphalt curing schedule required a longer cure time (manufacturer revised cure from 7— to 30 days), which shifted the timeline for sod installation and field surfacing. The team said that schedule change pushed back some turf and site work by several weeks.
Specialty work and permits At Escalante, presenters described a complex air-handler replacement that requires cutting openings into the existing enclosures and coordinating crane and pad work to remove large equipment without compromising roof structures. The district said it had received a state permit invitation-to-bid and had scheduled contractor bid dates with the aim of board consideration in August and construction start in September; an eight-month construction timeframe was projected for the larger package.
Site improvements, furniture and technology Staff said they executed a contract for asphalt/concrete site work and that a furniture package and technology scope for administration buildings had been procured. The district also described Starlink as a short-term backup in some rural sites while longer-term fiber options remain under discussion with local providers.
New school planning and enrollment projections Project staff reviewed site planning and discussed the new school schematic design. At the $675-per-square-foot cost assumption used in planning, the team said the current budget supports about 70,000 square feet; a draft program of 71,500 square feet would require trimming roughly 1,500 square feet or adding flex spaces. Staff also cited demographer input that projects growth focused south and east of Florida Mesa and said planners are considering future expansion options and designs that would simplify later additions.
Why it matters The program update details the sequencing and risk points for multiple projects that affect when buildings will be ready for students and when the district will complete the bond-funded portfolio. Several schedule adjustments and supply-chain issues were flagged that could affect fall 2025 openings and athletic field availability.
Ending District staff will return with refined schedules and financial strategy once bid results and final costs are available; the board asked to be kept informed of any changes that would affect school openings or occupancy.