A proposed purchase-of-service agreement with the Impact Project was tabled after commissioners said they had received an 81-page contract late, had unresolved solicitor concerns and noted potential county funding exposure while the state budget remained unsettled.

The Carbon County Board of Commissioners tabled a proposed purchase-of-service agreement with the Impact Project on July 3, 2025, after several commissioners said they had not had adequate time to review the contract or receive solicitor advice and raised questions about the county’s financial exposure while the state budget remained unresolved.

"I'm not willing to vote on something until I hear from the solicitor that the concerns of Carbon County have been met," a commissioner said during discussion of the item, noting that the county received an 81-page contract the previous Friday and that the solicitor had not completed review. The motion to table was seconded and passed unanimously.

Commissioners described the county’s potential fiscal exposure if the program started without guaranteed state funding. One commissioner said the county would be "on the hook for $240,000" if the project proceeded without state budget assurances; the figure was presented during discussion as the commissioners assessed short-term cash-flow risk.

Other issues raised included whether the contract text was Carbon County–specific, how the program would be implemented in schools, the degree of buy-in from local district attorneys and school districts, how referrals would be handled, and whether the county would incur ongoing staffing costs (for example, adding caseworkers in school buildings). Commissioners also noted that similar programs in neighboring counties used different legal arrangements (memoranda of understanding in one county, direct contracts in another), and that Carbon County’s contracts must be signed by the board of commissioners.

County staff and the solicitor were directed to do the following before the matter returns to the board: - Complete solicitor review and return recommended contract edits that are specific to Carbon County; - Clarify the county’s short- and medium-term funding exposure and whether state funding would cover the county’s costs once/if appropriations are available; - Provide details about school-level implementation, reporting responsibilities and intended timelines; - Confirm whether the program’s startup timeline (commissioners were told it could take two years to be fully operational) affects the county’s cost schedule.

The motion to table the agreement was recorded as unanimous. Commissioners said they were not opposed to the program’s goals but required more time and clearer legal and budgetary assurances before committing county funds.